Midterms Could Delay the AI Buildout, Not Derail It
United StatesAI infrastructureElections & policyElectrification & the grid
Our summary
U.S. midterm politics will delay and geographically reshape AI infrastructure investment while extending the cycle rather than stopping it.
- Opposition over electricity bills, water use and local economic benefits is producing state-level and project-level constraints, with proposed pauses or conditional moratoria in Texas and Ohio and tighter approval scrutiny in Georgia.
- Morgan Stanley estimates that about 5 gigawatts of U.S. data center projects, equal to roughly 20% of the 2028 pipeline, will shift into 2029; capacity additions should be flat in 2028 before rising nearly 40% in 2029.
- Hyperscaler capital expenditure is expected to remain about $1.6 trillion next year and $1.8 trillion in 2028, supporting a delay scenario rather than a fundamental reduction in investment.
- The estimated U.S. data center power shortfall through 2028 is 44 gigawatts, or roughly 38% of projected demand, shifting the key bottleneck from computing equipment toward access to electricity.
- Large hyperscalers with a line of sight to 25% to 50% returns on investment can redirect spending, absorb higher costs and improve efficiency, while slower 2028 construction could weaken equipment orders and supplier margins.
Takeaway: Investors should favor power-secured facilities, faster electricity-access technologies and well-capitalized hyperscalers, while applying greater scrutiny to new construction financing and suppliers exposed to a delayed buildout.
Published by Morgan Stanley Research. Summary by HF Best Ideas.