Newer AI chips could expand the profit pool around data centres, but falling token prices and changing infrastructure requirements will make tenant and asset selection more decisive.
- European data-centre capacity absorbed 1.6 GW in Q2 2026, versus approximately 1.2 GW in full-year 2025, while short-term demand continues to exceed additions to live supply.
- Data centres accounted for around 41% of North American and European infrastructure M&A and greenfield transaction volumes through September 2026; strategic buyers represented about 55% of data-cententre M&A, up from 31% in 2025.
- L&G estimates that annual AI-lab token revenue could rise from about $21m/MW on Nvidia Hopper chips to approximately $86m/MW on Blackwell, while a neocloud charges $10m-$12m/MW and a data-centre operator earns $1.8m-$2.1m/MW in annual rent.
- Blackwell's liquid-cooling requirement raises capital expenditure and creates obsolescence risk, while bringing power online one year earlier may generate more revenue than the approximately $42m lifetime power-cost difference between the UK and Norway.
- Weighted average token prices fell from $2 per million tokens in the first half of 2026 to below $1 by September, although AI-chip rental prices remained comparatively resilient; closed models may preserve margins, whereas open models could stimulate usage while compressing revenue per token.
Takeaway: Digital infrastructure remains attractive, but investors should prioritise time-to-power, delivery certainty, liquid-cooling capability and tenants using efficient chips, while recognising that value may shift among AI labs, neoclouds and data-centre operators as token prices and chip economics evolve.